nbn introduces DOCSIS 3.1 NTDs this month

No high-speed tiers to accompany launch of higher speed network

The company responsible for building the National Broadband Network, nbn, is set to begin installing new HFC Network Termination Devices (NTDs) at the end of this month to allow them to connect to the upgraded DOCSIS 3.1 network.

nbn’s NTD is a customised CM8200B DOCSIS 3.1 modem from Arris, who successfully won a tender to supply the network equipment.

nbn's new HFC Network Termination Device capable of DOCSIS 3.1
nbn’s new HFC Network Termination Device capable of DOCSIS 3.1 (Source: nbn co)

nbn had initially planned to begin deploying its DOCSIS 3.1 NTDs in December 2016. This has been pushed back by a month to the end of January 2017, with the company issuing an amendment to its Wholesale Broadband Agreement (WBA2).

In their notification letter to Access Seekers, nbn states that it intends to “introduce the new CM8200B (DOCSIS 3.1) HFC-NTD deploying on all HFC installations from end January 2017”.


No speed increase despite upgrade

Despite touting the speed capabilities of the new DOCSIS 3.1 modems, nbn will not launch new speed tiers to accompany the launch of the new modems.

In November 2015, nbn’s Chief Technology Officer penned a blog post saying that new modems by Arris will be capable of delivering “a stunning 5Gbps downstream and 2Gbps upstream”.

However, the maximum speed tier nbn will offer over the HFC network will remain at 100/40 Mbps. The January 2017 Integrated Deployment Plan also shows no future plans to introduce higher speed tiers already available the NBN Fibre network.

DOCSIS 3.1 promises to provide improved network performance and speeds through increased modulation orders and wider spectrum utilisation.

The new NTD will also have a second Ethernet port, however, the port will be disabled and covered by a sticker at launch.

NBN to rebate for higher speeds

Service providers may be eligible for a rebate to upgrade existing users to higher speed tiers

The company responsible for building the National Broadband Network, nbn, will introduce a three-month credit scheme designed to promote the uptake of higher speed tiers on its network.  The “Step Up AVC Credit” will see service providers refunded up to $33 over 3 months for upgrading existing customers to a higher speed tier.

End users must stay on the new tier for a minimum of 90 days to be eligible for the credit.

Rebates range from $9 to $33 over 3 months:

  • 12/1 Mbps to 25/5 Mbps: $9 over 3 months
  • 12/1 Mbps to 50/20 Mbps: $21 over 3 months
  • 12/1 Mbps to 100/40 Mbps: $33 over 3 months
  • 25/5 Mbps to 50/20 Mbps: $21 over 3 months
  • 25/5 Mbps to 100/40 Mbps: $33 over 3 months
  • 50/20 Mbps to 100/40 Mbps: $21 over 3 months

In an effort to reduce congestion and lower CVC congestion, the credit has strict guidelines about the state of congestion within the network.  Any connectivity virtual circuit connected to end users applying for the “Step Up AVC Credit” cannot exceed an average of 95% of network utilisation for 4 consecutive 15 minute intervals in any 24 hour period.

During this campaign, nbn will also co-fund marketing activities associated with the “Step Up AVC Credit” at $1.50 for each eligible AVC.

The scheme will start in November 2016 and finish at the end of March 2017.

[Source: NBN Co]

NBN Fibre to the Node Trial at Umina Beach

NBN to remediate business connections over copper

But will lock you in for 12 months if the existing copper line isn’t up to scratch

The company responsible for building the National Broadband Network, nbn, will begin offering line remediation to business services unable to reach their committed speeds over the copper network.

Business level services delivered over Traffic Class 2 (TC-2) have a committed information rate (CIR) which effectively guarantees a connection’s transfer rate.  Typical residential services are provisioned over Traffic Class 4, which has a peak information rate (PIR) describing the “up to” transfer rate achievable over the line.

The company is already offering TC-2 services over its FTTN and FTTB network with symmetrical transfer speeds of 5, 10 or 20 Mbps.  However, according to the current Wholesale Broadband Agreement (WBA), the company is currently not committing to its Committed Information Rate — stating:

“the actual Information Rate experienced by Customer, Downstream Customer or the relevant End User, may each be significantly less than the downstream CIR and upstream CIR of the bandwidth profile ordered by Customer in respect of the relevant Ordered Product”

According to the revised WBA on its website, the company will enable customers to submit a trouble ticket to remediate the copper line.  However, nbn will also require the end user to take up the service for at least 12 months or will have to pay an early disconnection or modification fee.

NBN will charge an early termination or modification fee if customers had their line remediated
NBN will charge an early termination or modification fee if customers had their business line remediated

Increased FTTN performance objectives

nbn is also increasing its network availability operational target on the FTTN Network from 99.70% to 99.80%.  The agreement states that “operational targets are non-binding and aspirational”.

The new wholesale broadband agreement will become effective in early December 2016.

 

nbn launches Cell Site Access Service

Company does away with CVC, but will charge two pricing levels based on metro or regional classification

The company responsible for building the National Broadband Network, nbn, has released an interim agreement for its Cell Site Access Service (CSAS).  As previously reported, this product is designed for mobile service providers to connect its cell towers through the National Broadband Network fibre network.

The agreement includes a price list, indicating nbn’s intention to provide cell towers with blended traffic class product including a traffic class 1 and traffic class 2 access virtual circuit (TC-1/TC-2 AVC).  All access products include a 5 Mbps TC-1 AVC, with varying amounts of TC-2 bandwidth from 50 Mbps to 900 Mbps.

Unlike the residential/business focused product offered by nbn (NEBS), the CSAS price list and product specification bares no mention of the contentious connectivity virtual circuit (CVC) — the charge imposed by nbn to allow traffic to be carried over from the NBN to the provider’s network.

For the first time, nbn has offered differential pricing based on the classification of the point of interconnect.  Access components in metro and outer metro areas will be charged at a lower rate compared with regional areas.

For example, the base product which includes 5 Mbps TC-1 and 50 Mbps TC-2 comes in at $910 in metro and outer-metro areas.  However, the access charge will increase to $1,245 for cell towers connected to regional points of interconnect.

NBN Cell Site Access Service - AVC Pricing Table
NBN Cell Site Access Service – AVC Pricing Table, Source: nbn co ltd

CSAS Network Termination Device

nbn will be providing a specialised network termination device (NTD) for customers of the Cell Site Access Service.  Unlike the standard NTD available for residential connections, the CSAS NTD will only have one User Network Interface (UNI) which is accessible through a copper or optical port.

The customer is expected to produce 3 RU of rack space for the installation of the NBN fibre tray, power supply and NTD.

NBN CSAS NTD Layout, Source: nbn co ltd
NBN CSAS NTD Layout, Source: nbn co ltd

 

You can find the CSAS pricing list and product descriptions on the nbn website.

Updated 23rd September 2016: to include that CVC appears is not mentioned.

NBN HFC self-install to become default

HFC installation premium for customers with existing lead-ins amongst changes in latest NBN product roadmap

The company responsible for building the National Broadband Network, nbn, has updated its product roadmap for the third quarter of 2016. Here is a summary of some of the key changes:

HFC product

nbn’s HFC product launched at the end of last month in a limited footprint in Redcliffe region in Queensland (PR044). The company also recently signed a contract with six delivery partners to upgrade and rollout the existing Telstra HFC footprint for nbn’s use.

Self-install to become default
As part of the current rollout strategy, nbn will send an installer to install the HFC Network Termination Device (NTD) at the customer’s premises when a service is ordered. However, the company plans to implement an RSP install and customer install option by the end of first and second quarter of 2017 respectively (PR112, PR129).

Once this process is implemented, nbn will begin charging customers who already have an existing lead-in a professional NTD installation a fee if they request for one.

Other HFC planned products
Deployment of DOCSIS 3.1 NTDs remain on-track for upgrade by the end of 2016 (CE045).

nbn also plans to introduce service transfers on HFC by September 2016 (PR121), as well as various diagnostic capabilities for Traffic Class 1 services.

The company does not plan to offer business grade “Traffic Class 2” tiers over HFC until 2018 or beyond (PR118).

NBN Satellite Service

ISS migration period extended
The migration of nbn’s existing Interim Satellite Service (ISS) customers to the new “Sky Muster” Long Term Satellite (LTS) service has been extended out until February 2017 (PR023). nbn had originally planned to migrate all its existing ISS customers to the Long Term Satellite solution by the end of 2016.

However, teething issues appeared to have hampered the originally anticipated activation rate — shifting the expected end date for the migration by two months.

There have been numerous reports of missed appointments, inability for NBN NTD modems to reconnect after a power reboot and most recently, the decision to retain the existing ISS satellite service after an LTS installation and retrospectively visit the customer to remove the ISS dish.

Consultation on “Managed Services Education” over Satellite
nbn is investigating the possibility of providing enhanced services for distance education students. The company has listed a number of possible products including a managed unmetered data service and multicast video broadcast services over its LTS service. Consultation on this service is expected to begin in September 2017.

Consultation on “Satellite Mobility” which could enable services like on-board Wi-Fi or Internet access for emergency services in remote areas has also been pushed back slightly to September (PR123).

Cell Site Access Service

As reported earlier, nbn concluded its initial Cell Access trial and has begun offering a Cell Site Access Service (CSAS) test service in Beaudesert, Queensland (PR039).

NBN begins second Cell Access trial

National broadband company continues to develop product to allow mobile carriers to tap into their fibre network

The company responsible for building the National Broadband Network, nbn, has released details of its proposed Cell Site Access Service (CSAS) — designed to allow mobile carriers to connect their mobile towers using NBN infrastructure.

This comes as nbn finishes their first round of trials with their customers which started at the end of 2013 and continued through till June this year. However, given the duration of this second trial which is not expected to end till July 2017, it appears that initial plans to have a cell site access product available to customers by the end of the year will be pushed back further.

Former CEO of Vodafone Australia and now NBN-CEO was once a strong advocate for the introduction of the backhaul service. However, the company recently signed a deal with TPG telecom to build out its fibre network to all of Vodafone’s cell sites.

According to the updated testing agreement, nbn will trial the CSAS at a “mobile complex” in Beaudesert, Queensland where the company has begun rolling out its fibre to the node and fixed wireless network. As part of the service, the carrier will receive a network extension quote equivalent to one from the company’s “Technology Choice Program” to extend the fibre network (FTTP) to the designated cell site.

During the trial, the company will not charge the participating carrier for this network extension or any associated costs with this service including the Access Virtual Circuit (AVC), User Network Interface (UNI), Connectivity Virtual Circuit (CVC) and Network-Network Interface (NNI) — however, it says it will intend to do so once the trial is completed.

The test agreement also makes mention of potentially co-locating the cell tower with towers used by NBN’s Fixed Wireless service as part of a facilities access agreement with the access seeker. The NBN company will also determine the network traffic class used during the trial.

The CSAS trial is expect to continue until 1st July 2017.

Source: Cell Site Access Service, Testing Agreement

The irony of NBN’s satellite numbers

After spending millions on consultants to criticise past decisions in the 2013 NBN Strategic Review, the company responsible for building the National Broadband Network, NBN Co, has repeated supposed past mistakes in a metric definition.

The review was highly critical of the former management of NBN Co when it stated that its Interim Satellite Service (ISS) had passed 250,000 premises when the satellites only had capacity to service 48,000 premises:

NBN Co has previously reported Satellite premises covered as 250,000, however the Independent Assessment considers that it is more appropriate to report 48,000 Premises Passed given the contractually limited capacity of the ISS.

NBN Co Strategic Review, Page 50

Consequently, the review revised the company’s performance figure down in the review — stating the former management had missed the target of 250k premises by 80% (page 40) by reclassifying the meaning of the metric.

Strategic Review says that NBN Co has missed their Corporate Plan target by 80% by "reclassifying" the meaning of Satellite Premises Passed
Strategic Review says that NBN Co has missed their Corporate Plan target by 80% by “reclassifying” the meaning of Satellite Premises Passed

Yet, three years later — here we are again with the company using the total satellite footprint as their headline “Premises Passed and Ready for Service” figure.

NBN Co’s weekly progress report, which provides a high-level summary of premises passed across Australia, says 404,064 premises have been “covered” by the Long Term Satellite service. Yet, in the 2016 corporate plan, the company states that satellites only has the capacity to service 250,000 premises at a time.

Following the footsteps of the Strategic Review, NBN Co will technically miss its corporate plan satellite target by around 50%.

NBN Co reports 404,064 premises covered by satellite as at 16th June 2016, yet the satellites can only handle 250,000 premises.
NBN Co reports 404,064 premises covered by satellite as at 16th June 2016, yet the satellites can only handle 250,000 premises.

The hilarity of it all

What can I say? Metrics are arbitrarily defined by those who want to portray a specific outcome. Criticism of metric definition is moot, and really occurs only when trying to pursue a line of argument intended by those writing it. The Strategic Review is an excellent example of this.

Perhaps unnoticed by many at the time, the numbers in the review favoured the Multi-Technology Mix even though there was no increase in capacity for the satellite.

The review considered only 206,000 premises passed by FY16 in the “revised outlook” — however, it magically jumped up to 340,000 premises passed in the adopted “multi-technology” case without any physical changes to the satellites.

NBN's satellite apparently passes 340k by FY16 premises in the MTM model
NBN’s satellite apparently passes 340k by FY16 premises in the MTM model
... yet in the revised outlook, only 206k premises are passed with satellite even though there are no changes to the satellite
… yet in the revised outlook, only 206k premises are passed with satellite even though there are no changes to the satellite

Remarkable isn’t it? Just goes to show how a metric can be reclassified to portray missed targets, then rapidly reclassified again to make your own rollout model look better 😉

Widespread delays plague Multi-Technology rollout

Analysis: Some areas delayed by up to 8 months, with 290k premises delayed by at least a month

The company responsible for building the National Broadband Network has updated its rollout schedule, revealing wide ranging delays of over a month in 105 multi-technology mix (MTM) rollout areas around Australia, affecting around 290,000 premises.

These rollout areas predominantly uses the Coalition’s preferred Fibre to the Node (FTTN) technology, where the company rolls out fibre to the neighbourhood and reconnects with the existing copper to the home.  Despite promising rollouts using the FTTN technology to be faster to complete, the company had reportedly been facing issues including slow rollout design approvals from power companies who will have to power the nodes in the streets.  The reasoning behind the latest set of delays is unknown.

The areas worst affected by the delay are Cygnet in Tasmania and Mornington in Victoria, with a delay of 8 months shifting completion dates from late 2016 to mid 2017.  The is followed closely by another rollout area in Mornington, Victoria as well as South Hobart and Margate in Tasmania and Garfield in Victoria with delays of between 6 and 7 months.

The rollout in Fletcher, NSW and suburbs near Claremont, Hobart, Tasmania have been set back by around 5 months.  Another 8 rollout areas, covering around 22,400 premises in parts of Victoria, Queensland, Western Australia, Tasmania and New South Wales have been delayed by 4 months.

For a full list of affected areas, refer to the table below.

Another 22 areas, not listed below, were delayed by less than a month.

Service Area Module (SAM) Locality May completion date June completion date # of months delayed Approx number of premises affected
7CYE-01 Cygnet Oct-2016 Jun-2017 8 600
3MOR-02 Mornington 12-Aug-2016 Apr-2017 8 3400
3MOR-05 Mornington Sep-2016 Apr-2017 7 2300
7HOB-12 South Hobart, Wellington Park, Fern Tree Oct-2016 Apr-2017 6 1000
7MGT-01 Electrona, Lower Snug, Margate, Snug, Coningham Dec-2016 Jun-2017 6 2000
3GAR-01 Garfield, Longwarry, Bunyip 05-Aug-2016 Feb-2017 6 2300
2NLT-01 Fletcher Oct-2016 Mar-2017 5 3700
7NWT-02 Chigwell, Berriedale Oct-2016 Mar-2017 5 2800
3TAG-04 Traralgon Oct-2016 Feb-2017 4 2600
4IGH-01 Ingham Oct-2016 Feb-2017 4 3000
6RKH-01 Safety Bay, Rockingham Sep-2016 Jan-2017 4 3100
6RKH-04 Rockingham, Safety Bay, Cooloongup Sep-2016 Jan-2017 4 3500
6ARM-02 Cardup, Byford Nov-2016 Mar-2017 4 4700
7BUI-04 Hillcrest, Montello, Park Grove, Parklands, Burnie Jan-2017 May-2017 4 1800
7HUL-01 Huonville, Ranelagh, Franklin Jan-2017 May-2017 4 2600
2GUL-01 Gulgong 15-Jul-2016 Nov-2016 4 1100
2NRN-01 Spring Farm Nov-2016 Feb-2017 3 800
7DER-04 Don, Stony Rise, Devonport Nov-2016 Feb-2017 3 3000
4SHF-02 Trinity Beach Sep-2016 Dec-2016 3 3200
2SHH-04 Flinders, Blackbutt Jan-2017 Apr-2017 3 3300
7ETD-01 East Devonport, Ambleside Dec-2016 Mar-2017 3 2600
7DSF-01 Dodges Ferry, Forcett, Lewisham, Primrose Sands, Carlton Dec-2016 Mar-2017 3 4300
7DER-03 Miandetta, Quoiba, Spreyton, Stony Rise, Tugrah, Aberdeen Jan-2017 Apr-2017 3 2900
3TAG-06 Traralgon 19-Aug-2016 Nov-2016 2 3400
2GLB-03 Run-o-Waters, Goulburn 22-Jul-2016 Oct-2016 2 2600
4WUR-09 Minyama, Buddina 08-Jul-2016 16-Sep-2016 2 3400
3MOE-03 Newborough, Moe 29-Jul-2016 Oct-2016 2 2800
2GLB-02 Goulburn 29-Jul-2016 Oct-2016 2 3200
3CRB-06 Craigieburn 29-Jul-2016 Oct-2016 2 4400
2GLB-04 Goulburn 22-Jul-2016 23-Sep-2016 2 2900
2ALB-01 South Albury, Albury 29-Jul-2016 30-Sep-2016 2 3600
7BUI-01 Emu Heights, Havenview, South Burnie, Wivenhoe, Burnie Dec-2016 Feb-2017 2 1200
3TAG-03 Traralgon East, Traralgon Sep-2016 Nov-2016 2 3100
4EDG-08 Kanimbla, Whitfield, Brinsmead Sep-2016 Nov-2016 2 2600
4FRV-01 Norman Gardens Sep-2016 Nov-2016 2 3300
7HOB-11 Moonah, New Town, Lenah Valley Sep-2016 Nov-2016 2 3000
3WBO-01 Warrnambool Sep-2016 Nov-2016 2 3700
7HOB-10 Sandy Bay Oct-2016 Dec-2016 2 3000
2BUP-03 Doyalson, Wyee, Blue Haven Nov-2016 Jan-2017 2 3100
2NRN-06 Harrington Park Nov-2016 Jan-2017 2 1800
3RYE-01 Rye Nov-2016 Jan-2017 2 4000
4BWE-01 Bowen Nov-2016 Jan-2017 2 2200
5MIC-01 Millicent Nov-2016 Jan-2017 2 2600
3CBR-64 Coburg North,Preston (Vic.),Reservoir (Vic.) Sep-2016 Nov-2016 2 1200
2BUP-01 San Remo, Buff Point 05-Aug-2016 Oct-2016 2 3200
3COL-02 Colac East, Elliminyt, Colac 05-Aug-2016 Oct-2016 2 3900
2MAI-09 Maitland, Telarah, Lorn 15-Jul-2016 09-Sep-2016 2 3300
3WAN-01 Wangaratta 15-Jul-2016 09-Sep-2016 2 3000
2MAI-06 Bolwarra Heights, Largs, Mindaribba, Bolwarra 22-Jul-2016 16-Sep-2016 2 2200
2ALB-04 North Albury, Albury 05-Aug-2016 30-Sep-2016 2 3400
2AVA-02 Avalon 05-Aug-2016 30-Sep-2016 2 2900
2MAI-01 Windella, Rutherford 12-Aug-2016 30-Sep-2016 2 1000
3MOE-04 Yallourn North, Newborough 19-Aug-2016 Oct-2016 1 3300
2MSV-03 East Bowral, Bowral 15-Jul-2016 26-Aug-2016 1 3500
2ALB-03 West Albury, Albury 29-Jul-2016 09-Sep-2016 1 3700
3SHP-09 Kialla West, Kialla 29-Jul-2016 09-Sep-2016 1 1500
2MTT-01 Mittagong, Willow Vale, Braemar 12-Aug-2016 23-Sep-2016 1 2000
4EDG-07 Earlville, Mooroobool, Bayview Heights 26-Aug-2016 Oct-2016 1 3400
3WAN-02 Wangaratta 15-Jul-2016 19-Aug-2016 1 2900
3WGU-04 Drouin East, Drouin 22-Jul-2016 26-Aug-2016 1 3400
7DER-01 Devonport 05-Aug-2016 09-Sep-2016 1 1800
2ERN-03 Green Point, Erina 12-Aug-2016 16-Sep-2016 1 3200
2KTB-02 Leura, Medlow Bath, Katoomba 12-Aug-2016 16-Sep-2016 1 3400
3WGU-05 Drouin 19-Aug-2016 23-Sep-2016 1 2800
4NEW-06 Cranley, Gowrie Junction, Torrington, Wilsonton, Wilsonton Heights, Cotswold Hills Dec-2016 Jan-2017 1 3300
2SHH-01 Shell Cove, Shellharbour, Dunmore Jan-2017 Feb-2017 1 3000
2NRN-05 Narellan, Narellan Vale, Elderslie Oct-2016 Nov-2016 1 2900
2PKE-05 Lake Heights, Berkeley Oct-2016 Nov-2016 1 3900
5GPC-05 Pooraka, Para Hills West Oct-2016 Nov-2016 1 3700
2PKE-02 Lake Heights, Warrawong, Cringila Oct-2016 Nov-2016 1 3700
3LOR-20 Lorne Oct-2016 Nov-2016 1 2500
3RMS-01 Romsey, Lancefield Oct-2016 Nov-2016 1 2700
3SUN-01 Sunbury Oct-2016 Nov-2016 1 3300
2NRN-03 Narellan Vale, Smeaton Grange, Harrington Park Oct-2016 Nov-2016 1 3800
4BDA-20 Babinda Oct-2016 Nov-2016 1 800
4FRV-03 Koongal, Lakes Creek, Nerimbera, Frenchville Oct-2016 Nov-2016 1 4300
4SAR-01 Sarina Oct-2016 Nov-2016 1 1900
6RKH-05 Waikiki, Cooloongup Oct-2016 Nov-2016 1 3700
6RKH-03 East Rockingham, Hillman, Rockingham, Cooloongup Dec-2016 Jan-2017 1 3300
6RKH-06 Waikiki, Safety Bay Dec-2016 Jan-2017 1 3500
6RKH-08 Rockingham, Peron Dec-2016 Jan-2017 1 3900
7CLT-01 Campbell Town Jan-2017 Feb-2017 1 700
5GPC-07 Mawson Lakes Jan-2017 Feb-2017 1 3600
3WDG-01 Wodonga, Leneva Sep-2016 Oct-2016 1 2700
3WAN-03 Wangaratta, Waldara Sep-2016 Oct-2016 1 1700
4NEW-09 Drayton, Harristown, Darling Heights Sep-2016 Oct-2016 1 3100
7EXE-01 Exeter, Gravelly Beach, Lanena, Rosevears, Swan Point, Blackwall Sep-2016 Oct-2016 1 900
4BUD-05 Palmwoods Sep-2016 Oct-2016 1 2100
4ROT-01 Rockhampton City, Depot Hill Sep-2016 Oct-2016 1 1400
4RED-01 Mount Cotton, Carbrook Sep-2016 Oct-2016 1 3000
4SHF-01 Trinity Beach, Trinity Park, Kewarra Beach Sep-2016 Oct-2016 1 1900
7NOL-01 Magra, New Norfolk, Lawitta Sep-2016 Oct-2016 1 2900
5BDT-20 Bordertown Nov-2016 Dec-2016 1 1600
7BIC-01 Bicheno Nov-2016 Dec-2016 1 900
5BRR-01 Berri Nov-2016 Dec-2016 1 2500
6ARM-01 Byford, Darling Downs, Haynes, Hilbert, Mount Richon, Wungong, Brookdale Nov-2016 Dec-2016 1 4000
6ARM-04 Forrestdale, Haynes, Seville Grove, Armadale Nov-2016 Dec-2016 1 3600
3MOE-01 Trafalgar, Moe 22-Jul-2016 19-Aug-2016 1 2700
6MDR-10 Erskine 27-May-2016 24-Jun-2016 1 2500
3PTO-05 Portarlington 15-Jul-2016 12-Aug-2016 1 2200
3PTO-06 St Leonards 15-Jul-2016 12-Aug-2016 1 2800
3OCG-02 Breamlea, Barwon Heads 22-Jul-2016 19-Aug-2016 1 2800
3SHP-10 Kialla 29-Jul-2016 26-Aug-2016 1 1300
7BUI-03 East Cam, Ocean Vista, Park Grove, Parklands, Shorewell Park, Cooee Feb-2017 Mar-2017 1 2900
7ETD-02 Latrobe Feb-2017 Mar-2017 1 2000

Analysis based on NBN Co’s rollout schedule, reproduced by Telstra on the Telstra Wholesale website.  A variety of sources were checked to confirm this information.

Why is HFC and FTTN still in Labor’s NBN?

The Labor party today released its NBN policy, just three weeks out from polling day.  The party has pledged to ensure around 2 million more homes and businesses will get Fibre to the Premises (rather than Fibre to the Node) — but will retain the HFC portion of the network.

I’m keeping it brief today because of exams… but one may wonder why the Labor party will not also pledge to move some of the HFC premises to Fibre to the Premises.  Further, why only shift 2 million premises to fibre?  That’s because of one word: contracts.

HFC contracts

NBN has already signed numerous contracts with various vendors and companies. Most recently, a $1.6 billion dollar contract with Telstra to rollout the HFC network.  Previously, a $400m contract with ARRIS to provide the equipment for the HFC upgrade.  Not to mention, all of the capital that has already been spent on building out the HFC IT systems (OSS/BSS).

In addition to this — the NBN company, under its Definitive Agreements with Telstra, must also retain ownership of the entire Telstra HFC network as soon as they switch on a single HFC-connected premises. That’s expected to occur within the next few weeks.

So even if the Labor party did pull the pin on the HFC network, not only will the NBN be liable for terminating contracts worth billions — it may also have to maintain a network HFC network (with Foxtel will continue to use) effectively for free even though NBN themselves won’t use it. Now that, would be absolute absurdity.

FTTN contracts

Estimates puts the build contracts signed by the end of July 2016 to be ~2 million premises (according to the leaked November 2015 IDP).  The last corporate plan puts the number of FTTN/B premises by the end of 2020 to be 4.5 million, leaving 2.5 million premises available to be switched to the Fibre to the Premises model.

Being able to switch turn around, complete new all-fibre network designs and sign contracts within one month would be wishful thinking.  This gives them around a 0.5 million premises buffer (mind you, that’s only gives them until October 2016) to turn around new designs and begin signing contracts or risk further delays.

Fortunately, there is no need to renegotiate the definitive agreements with Telstra and Optus again.  However, I’d still characterise the 2 million premises FTTN to FTTP shift as an “optimistic target”.  Good luck with the 4 month turnaround.

LNP backflip: “announcing” FTTN for West Coast Tasmania

NBN and the Coalition backtracks after facing massive community backlash for forcing thousands of homes and businesses in west coast Tasmania onto satellite

It’s possibly the height of hypocrisy.  The Government who led the charge to remove fixed-line communications in thousands of homes and business in Tasmanian West Coast communities is now “announcing” that they’re rolling out Fibre to the Node (FTTN) and Fixed Wireless networks in the townships of Queenstown, Rosebery, Zeehan and Strahan after massive community backlash.

Queenstown, the largest of the communities, already has existing fixed-line infrastructure including ADSL2+ and 4G mobile connections provided by Telstra.  The initial commitment by the former NBN-management was to rollout Fibre to the Premises (FTTP) to Queenstown, Rosebery and Zeehan.  This later changed to Fibre to the Node (FTTN) when the Coalition’s preferred Multi-Technology Mix model was introduced.

However, jxeeno blog’s analysis of the 18 month construction plan last July showed these areas were removed from the Fixed-Line rollout schedule.  It was later revealed in a Senate hearing that these towns were permanently removed after from the fixed-line rollout in favour of the long term satellite service.  This is despite the Coalition’s initiated Strategic Review modelled that the satellite beam servicing west coast Tasmania will likely be “severely oversubscribed”.

Up until this week, Queenstown remained the largest suburb covered entirely by the Long Term Satellite Service — originally intended for remote communities.

After strong community resistance arguing that their “new” national broadband network connections will be worse than their existing ADSL2+ services (in terms of latency and data allowances) and continued questioning by Tasmanian Labor Senator Anne Urquhart in various Senate hearings — it looks like for once, politics and community resistance has finally made a difference to the National Broadband Network’s so-called Multi-Technology Mix.

Now only if the broader outcry for reforming the Multi-Technology Mix is heard.